From a car yard to a fuel station, to a hole in the ground for 4 years, this site is now the address of 53 one and two bedroom apartments, two ground floor retail tenancies and a two level basement car park.

Hacer Group commenced construction at end of January 2012, received the Occupancy Permit on 24 May, Practical Completion on 28 May and purchasers commenced moving in on 5 June 2013.

The team experienced countless challenges throughout the project, in particular the extent of finishes to the facade, internal stair case design, site access restraints and managing the adjoining neighbours and Council expectations.

Through all the challenges Hacer Group, PDS Group, Interlandi Mantesso Architects, WSP Lincolne Scott, Cardno and all the subcontractors worked together to deliver the Client, Avenue Projects, a high-end project of which to be proud.